Personal information protection policy

This site uses cookies to optimize your browsing experience and track how you interact with it. By clicking on “I accept”, you consent to the use of these cookies. For more details on how we process this information, see our privacy policy.

Where would you like to
share this page?

Menu
The URL address has been copied to your clipboard.

Roadwork and Projects

Protect your underground installations

The City is planning infrastructure projects (roads, water, and street lighting) from May to November 2026. Residences in planned work zones may be affected. Please advise teh City if your property has heated sidewalks or driveways, irrigation systems, or other underground installations. Click here for more information

Info-travaux map

 Capital Works Programme map

 Stay informed about ongoing work and projects

Visit the Citizen Portal to view municipal notices

Westmount Projects

August 2026 to August 2027

Reconstruction of Mountain Avenue

Project Summary

  • Work planned: Reconstruction of the roadway and streetlight infrastructure, including the installation of a new combined sewer system to improve stormwater management within the existing network.
  • Work area: Mountain Avenue, between Cedar Avenue and Sherbrooke Street
  • Start date: Week of August 17, 2026
  • Estimated duration: Approximately 16 weeks in 2026 (through the week of November 23) and 17 weeks in 2027 (through the week of August 30).
  • Contractor: Demix Construction, a division of CRH Canada Group Inc. 

Project Details

Construction work on Mountain Avenue, between Cedar Avenue and Sherbrooke Street, is expected to begin during the summer 2026.

The work will be done in two phases:

  • 2026 phase: Approximately 16 weeks, from the week of August 17, 2026, to the week of November 23, 2026.
  • 2027 phase: Approximately 17 weeks, from the week of May 10, 2027, to the week of August 30, 2027.

The work will include:

  • replacing a section of the existing brick sewer mains with 750 mm diameter concrete pipes;
  • installing 2,400 × 1,200 mm rectangular concrete conduit sections, including eight rectangular manholes at five locations, for the new combined sewer system;
  • relocating sections of the water main and natural gas main to provide adequate space for the new combined sewer system (please note that all gas-related work will be carried out by Énergir);
  • reconstructing the road infrastructure (granular base, concrete slab, and asphalt pavement);
  • reconstructing sidewalks to the standard minimum width of 1.5 m;
  • installing new streetlight conduits and luminaires;
  • road line painting.

Update—November 2026

Please be advised that preparatory paving work on Mountain Avenue between Cedar Avenue and Sherbrooke Street will exceptionally begin at 5:30 a.m. on Monday, November 9. The street will be closed to traffic to allow the work to proceed.

During this time, please avoid walking on surfaces where a bonding agent has been applied to prevent stains on clothing and private property.

The street is expected to reopen on the morning of Tuesday, November 10. Pavement marking work will follow during the week.

In the event of unfavourable weather conditions, the work will be postponed to the next suitable day.

Yield Street

As part of the reconstruction project, Mountain Avenue will be officially converted into a two-way yield street. This change is being put in place in particular due to the unique topography of this corridor.

  • Managing incline safety: On steep slopes like Mountain Avenue, giving priority to northbound (uphill) traffic allows vehicles to maintain necessary momentum. Requiring southbound (downhill) drivers to yield forces traffic moving downhill—which naturally picks up speed—to slow down and navigate the section with extra caution.
  • Prioritising pedestrians: Keeping the roadway narrow allows the City to widen sidewalks and add streetscape landscaping, creating a safer environment for pedestrians.

Learn more

Construction Site Safety

To help ensure everyone's safety during construction, residents are reminded to follow these precautions:

  • Stay alert to your surroundings when walking on sidewalks near the construction site.
  • Do not cross through the construction zone or enter barricaded areas.
  • Keep a safe distance from operating machinery, equipment, and construction vehicles.
  • Contact a flag person or a member of the construction crew if you need to access a specific area or require assistance crossing safely.
  • Always follow temporary signage and traffic instructions.

Everyone’s cooperation is essential to maintaining a safe work environment for both residents and construction workers.

Residents

During the reconstruction of the sidewalks, some work may temporarily extend into private landscaping located within the public right-of-way (such as lawns, walkways, and driveway aprons). All affected areas will be restored by the contractor to their original condition or better upon completion of the work.

If you have a heated driveway, heated walkway, or irrigation system, please notify the Engineering Department at genie@westmount.org or 514-989-5200 (City main assistance line).

Portions of the water main and natural gas main will be relocated to provide adequate space within the public right-of-way for the installation of the new combined sewer system. Please note that some residents may experience a short interruption to their water service and/or Énergir natural gas service.

Parking and Traffic

On-street parking will be temporarily prohibited within the construction zone. Parked vehicles may interfere with the work and cause delays; please respect all posted No Parking signage.

At certain stages of construction, access to driveways may be temporarily restricted. Affected residents will receive 24 to 48 hours' advance notice.

During construction, Mountain Avenue will be temporarily closed to vehicular traffic. Appropriate detour signage will be installed to guide local traffic around the construction zone. Road closures and detour routes will vary throughout the different phases of the project.

Pedestrian access to residences will be maintained at all times.

Waste, Recycling and Compost Collection

Collection of all waste materials (garbage, recycling, food waste, yard waste, and bulky items) will continue according to the regular schedule.

Materials must be placed at the curb before 6 a.m. on collection day to allow the contractor to relocate bins if necessary. Please ensure that all bins are clearly identified with your address.

Share
August 2026 to summer 2027

Reconstruction of the Thornhill Staircase

Project Summary

  • Work to be completed: Reconstruction of the Thornhill staircase
  • Construction area: The pedestrian staircase connecting Stanton Street and Thornhill Street
  • Start date: Week of August 10, 2026
  • Estimated duration: until summer 2027
  • City investment: $896,805
  • Contractor: 9140-2594 Québec Inc. (Construction Arcade)

Project Details

  • Complete demolition of the existing staircase, including foundations, walls, steps, coping, guardrails and the lamppost.
  • Complete reconstruction of the staircase.
  • Consolidation and reinstatement of the existing stones, as well as installation of new stones in the retaining walls.
  • Installation of new handrails.
  • Enhancement of the existing lamppost and installation of new lighting.
  • Improvement of the drainage system.

Mobility and Parking

The work and construction site setup may cause temporary disruptions to vehicle traffic on Thornhill Avenue, as well as impacts on landscaping located within the municipal right-of-way. The contractor will reinstate all affected surfaces and restore them to their original condition at the end of the work.

A few parking spaces located near the entrance to the staircase on Thornhill Avenue and on Stanton Street will be temporarily occupied by the contractor. Access to Thornhill Avenue may also be restricted at certain times. Affected residents will receive 24 to 48 hours’ notice before any interruption of access. Pedestrian access to residences will be maintained at all times.

Mobilization plan

Share
July to October 2026

Claremont Avenue Rehabilitation and Lorraine Avenue Reconstruction

Project Summary

  • Work planned: Claremont Avenue roadway rehabilitation and Lorraine Avenue reconstruction
  • Work area: Claremont Avenue, between Lorraine Avenue and Sherbrooke Street, and Lorraine Avenue
  • Start date: July 13, 2026
  • Estimated duration: Approximately 9 weeks
  • Contractor: Les Entreprises Ventec Inc.

Project Details

As part of the City of Westmount’s Capital Works Program, street rehabilitation work will begin on July 13, 2026, on Claremont and Lorraine avenues.

The project includes:

  • complete reconstruction of Lorraine Avenue;
  • rehabilitation of the Claremont Avenue roadway, including localized foundation repairs;
  • reconstruction of sidewalks;
  • replacement of the public lighting system;
  • installation of a new storm sewer on Lorraine Avenue, including service connections to adjacent properties.

Update—November 2026

Claremont and Lorraine avenues will be completely closed to traffic from 5:30 a.m. on Wednesday, November 4, for paving of these streets. Exceptionally, work will begin earlier than usual to allow for the necessary preparations. The streets are expected to reopen the following morning.

In the event of inclement weather, the work will be delayed until the next favourable day.

Residents

As part of the sidewalk reconstruction, some work may temporarily extend onto private landscaping located within the municipal right-of-way (lawns, walkways, and driveways). All affected areas will be restored by the contractor to their original condition upon completion of the project.

If you have an irrigation system or a heated driveway, please notify the Engineering Department by email at genie@westmount.org (unless you have already done so earlier this year).

Mobility and Parking

Beginning July 13 at 7 a.m., access to driveways will be restricted, and on-street parking will be temporarily prohibited within the work zone.

Pedestrian access to residences will be maintained at all times.

Garbage, Recycling and Compost

Collection of all waste streams (garbage, recycling, organic waste, yard waste, and bulky items) will continue according to the regular schedule.

Please place your clearly labelled bins at the curb before 6 a.m. on collection day so that the contractor can move them if necessary.

Share
June to September 2026

Murray Hill Avenue Reconstruction

Project Summary

  • Work planned: Reconstruction of Murray Hill Avenue (road infrastructure and intersection improvements)
  • Work area: Murray Hill Avenue between Westmount Avenue and The Boulevard, including the Douglas and Grenville Avenue sectors
  • Start date: June 29, 2026
  • Estimated duration: Approximately 14 weeks
  • Estimated cost: Details will follow
  • Contractor: Cojalac Inc.

Project details

As of June 29, 2026, reconstruction work will be carried out on Murray Hill Avenue to improve road infrastructure and intersections in the area.

The work will include, in particular:

  • full reconstruction of the roadway;
  • improvements to the intersections of Douglas and Grenville avenues;
  • reconstruction of sidewalks and curbs;
  • work on underground infrastructure;
  • localized reconfiguration of roadway edges within the municipal right-of-way.

Update—September 2026

As of 7 a.m. on September 15, 2026, the road will be completely closed to traffic to allow the contractor to complete stone grading and paving work. The road will be reopened once the paving work has been completed, not before September 18, 2026.

Note that only the base layer of asphalt will be pave din the fall of 2026. The surface layer of asphalt will be completed in spring 2027, in accordance with City specifications. Temporary asphalt ramps will be installed to facilitate access to private driveways until the surface layer in completed.

Yield Street

As part of the reconstruction project, Murray Hill Avenue will be officially converted into a two-way yield street. This change is being put in place in particular due to the unique topography of this corridor.

  • Managing incline safety: On steep slopes like Murray Hill, giving priority to northbound (uphill) traffic allows vehicles to maintain necessary momentum. Requiring southbound (downhill) drivers to yield forces traffic moving downhill—which naturally picks up speed—to slow down and navigate the section with extra caution.
  • Prioritising pedestrians: Keeping the roadway narrow allows the City to widen sidewalks and add streetscape landscaping, creating a safer environment for pedestrians.

Learn more

Mobility and parking

Local access will be maintained as much as possible, particularly for residents of the area.

Garbage, recycling and compost

Waste collection will continue according to the regular schedule. However, when the street is inaccessible, collections will be managed by the contractor.

Bins must be placed at the curb by 6 a.m. on collection day and clearly labeled.

Consult the project presentation

Share
May to October 2026

Rehabilitation of Arlington Avenue and Sherbrooke Street West between Grosvenor Avenue and Strathcona Avenue

Project summary

  • Work planned : Reconstruction of Hydro Westmount underground infrastructure, rehabilitation of sidewalk sections, and roadway resurfacing
  • Work area: Sherbrooke Street West, between Grosvenor Avenue and Strathcona Avenue, as well as Arlington Avenue between Côte Saint-Antoine and Sherbrooke Street West
  • Start date: May 19, 2026
  • Estimated duration: Approximately 23 weeks
  • City's investment: $7,875,000
  • Contractor: Les Entreprises Ventec Inc.

Beginning Tuesday, May 19, resurfacing and infrastructure rehabilitation work will take place on Sherbrooke Street West, between Grosvenor Avenue and Strathcona Avenue, as well as on Arlington Avenue between Côte Saint-Antoine and Sherbrooke Street West. The project is expected to last approximately 23 weeks.

Project Details

The rehabilitation project on Sherbrooke Street West and Arlington Avenue includes the following work:

  • Reconstruction of Hydro Westmount’s underground infrastructure (electrical conduit network) beneath the north-side sidewalks*
  • Reconstruction of five Hydro Westmount access shafts located along the north side of Sherbrooke Street West
  • Full reconstruction of sidewalks on Arlington Avenue and along the north side of Sherbrooke Street West
  • Targeted reconstruction of selected sidewalk sections along the south side of Sherbrooke Street West
  • Removal of the asphalt surface, localized repairs to the road foundation, and complete resurfacing of Sherbrooke Street West and Arlington Avenue

*The improvements to the electrical network are essential to ensuring a safe and reliable power supply. These upgrades will not only help prevent potential outages, but also meet growing energy demands and replace aging equipment, thereby ensuring long-term service reliability for residents and businesses.

Project Schedule

To minimize impacts on businesses, residents, and traffic flow, the work will be carried out in several phases:

  • May 19 to mid-June: Reconstruction of Hydro Westmount infrastructure along the north side, between Grosvenor Avenue and Westmount Baptist Church
  • May 19 to mid-June: Targeted reconstruction of sidewalks and concrete crossings along the south side of Sherbrooke Street West, between Lansdowne Avenue and Strathcona Avenue
  • May 19 to late May: Reconstruction of sidewalks along the west side of Arlington Avenue
  • June to mid-July: Reconstruction of sidewalks and the lighting network along the east side of Arlington Avenue
  • Mid-June to mid-July: Reconstruction of Hydro Westmount infrastructure along the north side, between Westmount Baptist Church and Arlington Lane
  • Mid-June to July: Targeted reconstruction of sidewalks and concrete crossings along the south side of Sherbrooke Street West, between Grosvenor Avenue and Lansdowne Avenue
  • July: Reconstruction of sidewalks and concrete crossings along the north side of Sherbrooke Street West, between Grosvenor Avenue and Lansdowne Avenue
  • August: Reconstruction of Hydro Westmount infrastructure along the north side, between Arlington Lane and Strathcona Avenue, as well as construction of an electrical duct bank at the Victoria Hall BIXI station
  • August: Reconstruction of sidewalks and concrete crossings along the north side of Sherbrooke Street West, between Lansdowne Avenue and Arlington Avenue
  • August: Asphalt removal, localized road foundation repairs, and paving work on Arlington Avenue
  • Early September to mid-September: Reconstruction of sidewalks and concrete crossings along the north side of Sherbrooke Street West, between Arlington Avenue and Strathcona Avenue
  • Mid-September to late October: Asphalt removal, localized road foundation repairs, and paving work on Sherbrooke Street West

Paving Work

September 9 to 11: Cleaning and asphalt paving work will take place on Arlington Avenue, between Côte-Saint-Antoine Road and Sherbrooke Street West.

  • Arlington Avenue will be closed to traffic starting Wednesday, September 9 at 7 a.m., weather permitting.
  • The street is expected to reopen on Friday, September 11 at 7 a.m., weather permitting.
  • Residents must move their vehicles from the street and driveways before 7 a.m. on September 9 and use the temporary parking permits already provided for parking on nearby streets.
  • Vehicular access to private driveways will be prohibited during the work. Once reopened, Arlington Avenue will be accessible only from Côte-Saint-Antoine Road.
  • Pedestrian access will be maintained at all times.

Mobility and Parking

One traffic lane in each direction will remain open throughout the duration of the work on Sherbrooke Street West. Arlington Avenue will be closed to through traffic, with access maintained for local traffic only.

Pedestrian access, including access to all residences and businesses, will be maintained at all times.

On-street parking along Sherbrooke Street West will be optimized as much as possible during the work. However, parking restrictions and changes to parking availability may occur depending on the progress and specific phases of the project.

Designated areas for deliveries and short-term loading and unloading operations will be provided whenever possible.

Road Closures

Lansdowne Avenue and Sherbrooke Street intersection 

An electrical chamber reconstruction is scheduled at the intersection of Lansdowne Avenue and Sherbrooke Street. As a result, southbound traffic on Lansdowne Avenue at Sherbrooke Street, approaching from Côte Saint-Antoine Road, will be blocked. Lansdowne Avenue between Côte Saint-Antoine Road and Sherbrooke Street will be closed to through traffic and temporarily converted to two-way traffic for local residents only. Traffic will be detoured via Victoria Avenue. This closure is expected to last approximately five weeks. 

Rosyln Avenue and Sherbrooke Street intersection

Water works are scheduled at the intersection of Roslyn Avenue and Sherbrooke Street. As a result, southbound traffic on Roslyn Avenue at Sherbrooke Street, approaching from Côte Saint-Antoine Road, will be blocked. Roslyn Avenue between Côte Saint-Antoine Road and Sherbrooke Street will be closed to through traffic and accessible only to local residents. Traffic will be detoured via Victoria Avenue. This closure is expected to last approximately one week. 

Collection

Waste collection services will continue according to the regular schedule. Residents are asked to place their bins curbside before 6 a.m. and ensure they are clearly identified with their address so the contractor may relocate them if necessary.


Share
May to November 2026

Replacement of the Main Staircase Foundations at Victoria Hall

Project Summary

  • Work planned: Replacement of the main staircase foundations at Victoria Hall
  • Work area: Victoria Hall main entrance (Arlington Avenue)
  • Start date: Week of May 25, 2026
  • Estimated duration: Until the end of October 2026
  • City's investment: $465 293
  • Contractor: Conception PLHP Inc

This project involves the rehabilitation of the foundations and components of the main staircase at Victoria Hall due to the deterioration of the steps and landing. The work will help ensure the safety, durability, and compliance of this public entrance.

Project Details

The project includes several interventions, notably:

  • repair of the structure supporting the stone steps and landing;
  • repair of interior vestibule floor finishes;
  • replacement of door thresholds;
  • restoration of wooden doors (sanding and refinishing);
  • repair of damaged interior finishes (stone plinths and floor stones) at the main entrance;
  • repair of damaged interior finishes at the east side secondary entrance;
  • upgrading the main entrance handrails to meet current standards;
  • restoration of landscaping upon completion of the work.

Since excavation work is required, a construction zone will be established around the main entrance.

The work will be carried out in two phases to maintain functional access to the building:

  • Phase 1: Main entrance – structural work, excavation, and major repairs
  • Phase 2: Secondary entrance – finishing work and compliance upgrades

The main entrance will be closed for the duration of the works. Users will be directed to the secondary entrance, which will be clearly signposted on site. A secured section of the main entrance will remain in place for emergency exits only.

Mobility and Traffic

Arlington Avenue will be closed in front of Victoria Hall during the works, and a construction zone will be established around the main entrance to accommodate excavation and related activities.

Share
August 2025 to November 2026

Restoration of the Roslyn stairs

Project Summary

  • Work planned: Restauration of the Roslyn public staircase
  • Work area: Intersection of Upper Roslyn Avenue and The Boulevard
  • Start date: August 11, 2025
  • Estimated duration: 2 years
  • City's investment: $2,983,234 
  • Contractor: Saho Construction Inc.

This construction project will be carried to restore the Roslyn public stairs, which serve as an exterior public stairway connecting Upper Roslyn Avenue to The Boulevard. The project aims to ensure the safety, accessibility, and long-term preservation of this important public infrastructure.

Project Details

Some fo the key highlights of the project include :

  • demolition of the existing staircase structure while preserving the existing surrounding retaining walls;
  • reconstruction of a new staircase structure, maintaining an east and west branch layout that is similar to the existing design;
  • construction of two additional retaining walls within the central green space to mitigate soil erosion;
  • installation of five new 'park style' Washington light posts with their respective underground electrical conduit infrastructure, to enhance safety in the area;
  • integration of a bicycle ramp into the concrete stairs, starting along the west side of the lower and middle sections, and continuing along the east side of the upper section of the staircase;
  • installation of an aluminium metal handrail on both sides of the staircase, with a single central handrail on the initial staircase section coming from The Boulevard;
  • removal of existing vegetation and replanting of all green spaces, with the preservation of select trees.

This project is scheduled to be completed in two phases over two years:

  • Phase 1 is scheduled to begin on August 11 and conclude by the week of December 20, 2025. A temporary handrail will be installed on the east side of the staircase to facilitate pedestrian access during the 2025-2026 winter season.
  • Phase 2 is planned to begin during spring 2026, starting on April 20 and will continue for approximately 7 weeks. This phase will include the installation of new stone cladding, repairs to the staircase walls, landscaping, and the installation of the permanent handrail. [ Consult the notice ]

Mobility and Parking

Due to the scope of the construction project, the contractor will need to occupy several public areas for the duration of the work:

  • The Boulevard (northbound driving lane): This lane will be used as a material transport zone, an equipment storage container, and a site toilet.
  • Belfrage Road: A construction trailer will be placed on this street.
  • Upper Roslyn (cul-de-sac): This portion of the avenue will also be occupied.
Share
November 2026 to Spring 2027

Rehabilitation of the Holton and De La Vigne Staircase

Project Summary

  • Work planned: Structural rehabilitation of the public staircase
  • Work area: Pedestrian staircase connecting Holton Avenue and Chemin de la Vigne
  • Start date: November 18, 2026
  • Estimated completion: Spring 2027
  • Contractor: Les Entreprises Ventec inc.

Project Details

The City of Westmount will undertake structural rehabilitation work on the public staircase connecting Holton Avenue and Chemin de la Vigne.

The work will include:

  • reconstruction of a structural column supporting the staircase;
  • repairs to selected sections of the staircase structure;
  • dismantling of certain structural components, transporting them to an off-site workshop for restoration, and returning them to the site for reinstallation.

Pedestrian Access

The staircase will be completely closed to the public for the duration of the work, beginning November 18, 2026, until its expected reopening in spring 2027.

Access will be blocked at both ends of the staircase: the southern entrance near Holton Avenue and the northern entrance near Chemin de la Vigne.

Residents and pedestrians are encouraged to use alternative routes while construction is underway.

Share

Other projects impacting Westmount

No other project at the moment

No other project should impact Westmount.

Share

Consult the Ville de Montreal's resources for up-to-date information on projects that affect Westmount.

Montreal's website

Mobility Montreal

Public Transportation

Roadwork may affect public transportation bus routes and schedules. Find the most up-to-date information on the STM website.

Bus service updates

Please note that while Westmount does notify popular navigation apps (Google Maps, Waze, etc.) of road closures, the City has no control over what is published on these platforms.

Useful links

Roadwork Guide and Safety GuidelinesTraffic and SignagePotholes