Reconstruction of the Thornhill staircase, which began on August 10, will be suspended in early December for the winter season.
This year, crews fully demolished the old staircase, completed the main reconstruction work (foundations, walls, steps and landing), and installed a new drainage system.
Work will resume in spring 2027 with the stabilization and reinstallation of the existing stones, new stones to complete the retaining walls, and the installation of new handrails and light poles. The project is expected to be completed by late June 2027.
The staircase will remain closed and inaccessible to the public throughout the winter. The site will stay secured until work resumes.