The ministère des Transports wishes to inform you that work to finalize the construction of the Saint-Jacques bridge will be carried out from April 15 avril until August 2019.
The complete closure of the rue Saint-Jacques, between boulevard Décarie and avenue Girouard, will be required during this period.
WORK DESCRIPTION:
- Construction of bridge approaches
- FinaliZation of the lighting
- Completion work
From April 9 to September, operations will also be carried out in the area of avenue Prud’homme for the construction of new infrastructures including the laying out of the dead-end of the avenue.
WORK SCHEDULES:
Saint-Jacques bridge
- 6:30 a.m. to 5 p.m., Monday to Friday
Avenue Prud’homme
- Carried out continuously, Monday to Friday including embankment from 7 p.m. to 6 a.m.
Weekend operations may be required on an ad hoc basis.
For more information
514 873-1372
turcot.commentaires@transports.gouv.qc.ca
Twitter: @MTQ_Turcot
turcot.gouv.qc.ca